Planning
Project Execution Plan (Week-by-Week)
The plan below compresses the pilot into approximately 14 weeks. Pre-week 0 activities --- particularly biometric device procurement and infrastructure approvals --- should begin as soon as the pilot is approved.
Week 0
Kick-off, MOSIP introduction and *migration prep
MOSIP introduction; high-level demo of MOSIP, INJI and eSignet; acquire source data and database structure for any legacy migration in scope.
Week 1
Infrastructure readiness
Begin procurement and shipping of biometric devices; readiness check of on-prem or cloud hardware (compute, storage, networking); *continue acquiring legacy source data.
Weeks 2--3
ID schema, master data, customisation
Define country ID schema and master data; identify customisation needs; obtain SMS / email gateway details; start customisation; deploy MOSIP onto the country environment; *start data quality analysis for any legacy migration.
Week 4
Customisation, configuration and platform readiness
Publish data quality analysis; complete customisation; finalise email and SMS configuration.
Weeks 5--6
Integration and *migration utility
Build the legacy migration utility; integrate biometric components into the country environment; deploy ABIS, SDKs and the manual adjudication system; configure SMS in the platform.
Weeks 7--8
Pilot system readiness
User acceptance testing; functional training for the country technical staff; biometric functional training.
Weeks 9--10
Field readiness
Operator and supervisor training; migration training; field pilot preparation; calibration of registration Centers for go-live.
Weeks 11--14
Pilot go-live
Field execution: legacy migration, new registrations up to 3,000 residents, authentication exercises, INJI Wallet usage, helpdesk operation; pilot closure and report preparation.
This is just an indicative execution plan. The actual execution plan with dates to be prepared based understanding and agreement between the country and MOSIP team.
*For brown-field pilots only; a brown-field pilot re-uses issued National ID from a legacy system by migrating the ID data into MOSIP.
Critical dependencies
On-prem or cloud infrastructure and the necessary access for installation must be ready before the start of Week 1 or 2.
Biometric device procurement and shipping typically takes 6 to 8 weeks. The country team supports the customs clearance process.
The country lead finalises the ID schema and provides the master data inputs.
SMS and email gateway access is configured ahead of customisation completion in Week 4.
If you only do one thing in week 0 Place the biometric device order and lock the infrastructure environment. Everything downstream depends on these two long-lead items.

Figure 3 --- Indicative 14-week schedule. Country-led streams (navy), MOSIP-led / shared streams (teal) and critical-path / gate items (orange).
Roles and Responsibilities
Responsibilities are split between the country program and the MOSIP team. The matrix below covers technical resources, setup, rollout, management and procurement.
Technical resources
Country technical team
Country & field staff
Technical resources
MOSIP pilot deployment team
MOSIP
Technical resources
Government resource for ID schema and master data preparation
Country
Technical resources
Functional training; operator and supervisor training
MOSIP + Country
Technical resources
Field staff for registration
Country
Pilot setup
GitHub private account, Docker account creation and access
Country
Pilot setup
ID schema, master data
Country + MOSIP
Pilot setup
MOSIP deployment in the country environment
MOSIP with Country support
Pilot setup
Customisation
MOSIP
Rollout
Resident pre-registration
Country
Rollout
Resident registration at Centers, ID issuance
Country
Rollout
ID authentication using relying-party portal and INJI
Country
Rollout
Feedback, metrics collection, report generation
Country
Rollout
Pilot closure sign-off
Country + MOSIP
Management
Initial pilot plan
MOSIP
Management
Pilot plan finalisation
Country
Management
Pilot project management
Country + MOSIP
Management
Governance structure
Country + MOSIP
Procurement
On-prem / cloud environment
Country
Procurement
ABIS, biometric SDKs, manual adjudication system
MOSIP
Procurement
SMS / email gateway
Country
Procurement
SSL certificates
Country or MOSIP
Procurement
Biometric devices for registration and authentication (fingerprint slap scanner, dual iris scanner, fingerprint authentication device)
MOSIP
Procurement
Face camera for registration
Country
Procurement
PCs / laptops, printers and scanners
Country
Resourcing the Country Team
The country team is the Center of gravity of the pilot. They run the deployment, register residents, and inherit the system at sign-off --- so resourcing them well is the single biggest predictor of success.
Project Manager
1
Owns the country program. Reports to the steering committee, manages dependencies, and signs off the pilot.
Senior Technical Lead
1 or more
Functional and technical owner of MOSIP within the country team. First point of contact for field issues. Becomes the in-house MOSIP expert for future scale.
Junior Technical Engineers
3 or more
Hands-on engineers handling deployment support, configuration, integrations and incident response.
Field Operators
5 or more
Run the registration kits at the Centers. Identified, trained and certified by the country team.
Field Supervisors
1 per registration Center
Supervise operators, manage exceptions and run the day-to-day helpdesk.
Adjudicators
1 or more
Handle manual adjudication for biometric duplicates and quality exceptions.
Communications focal point
1
Coordinates resident outreach, appointment scheduling and notification content for SMS and email.
Identify operators and supervisors early Operators and supervisors must be identified by the country team well before the training window. Onboarding is hands-on and assumes participants are available for a continuous training block, not part-time.
Governance and Review Cadence
A lightweight, predictable governance structure keeps decisions moving without burying the technical team in meetings.
Pilot Governance Committee
Country representatives, MOSIP, key stakeholders. Set up during kick-off.
Pilot kick-off and at major milestones.
Weekly technical review
Country and MOSIP technical Leads
Weekly or as discussed in the kick-off meeting, throughout the pilot
Steering committee
Executive members from the country and MOSIP.
Bi-weekly or at gate decisions.
Pilot readiness review
Members of the Steering Committee, Tech leads from the country and MOSIP
After User Acceptance Testing
Closure meeting
All stakeholders
After registrations are completed; final sign-off.
Always close with lessons learned Block the last 30 minutes of each weekly review for 'what surprised us this week'. The compiled list becomes the lessons-learned annex of the closure report. It also helps in mid-course corrections during the pilot.